Date of project: May 2015
Key objectives: Upgrade of ship’s equipment to meet latest classification and statutory requirements
Project location: Worldwide
Key barriers/issues: Engineering challenge
Key achievements: Flexible approach, creating a product meeting specific customer needs (all in one package, enabling the crew to carry out the installation and commissioning).
Project description
Customer contacted AtZ Marine as they needed to upgrade their existing oily water separator systems to meet latest classification and statutory requirements.
AtZ Marine designed a retro-fit package to supply in total 7 vessels with new OMD-2005 measuring units whilst keeping original oily water separators unchanged. AtZ Marine installed and commissioned the first unit and was then able to supply the remaining 6 vessels with a commissioning kit including not just the new measuring units, but also all pipe works and parts required with shore assistance allowing the ships crews to carry out the installation and commissioning anywhere in the world.